New Building Construction: Progress Update 29

General

Cranes & Fork Lifts:- Tower Crane TC2 is being used to secure the reconstituted stone fins. The south block is served with tower crane TC1 and will be supplemented occasionally with a small “city crane” and a roof “spider” crane . Internal materials are largely served by a fork lift and with use of the tower crane when required.

Sample Rooms:- Three “early” office rooms are in progress with skirting, door frame and door installations followed shortly by service finals and carpet.

Visits:- The Mathematics Department tour took place on the 9/11/2012.

Future works for November

Architectural Metalwork:- After completion of the steel frame balustrade, the next installations will be the main entrance staircase and basement stairs due at the end of the month.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- The perimeter to roofs are continuing to the south block and core roofs.

Cladding:- Corner units continue to be installed on the north block. The south block continues along both east and west elevations and has also started on the NE elevation above the Entrance.

Glass Atrium Roofs:- The north atrium roof has the main area largely installed with glass. The south minor atrium has the main support beams installed, while south major is being drilled in readiness for steelwork.

Reconstituted Stone:- Techrete are progressing on the north block with the stone fins that surround the windows on the north.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to be complete by early December. The passenger lift to the south has the safety gates installed ready to install at the end of November.

Mechanical & Electrical:- The majority of plant has been delivered except the generator which is due imminently. Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine.

Internal Fitout:- Plasterboard walls are progress to all zones of the north block. The raised floor commence on 12/11/2012 to the first area of the north block 1 week ahead of programme. On the South block the first zones E&F have commenced on 12/11/2012 in line with programme.

Recent Site Photos

[bg|new-building/site-visits/20121115|0]
Please contact us with feedback and comments about this page. Created on 16 Nov 2012 - 09:48.

Titchmarsh Fellowships

The Mathematical Institute has just announced the availability of up to 4 prestigious Titchmarsh Fellowships in a range of subjects including mathematical and computational finance. Applications are due on December 10, 2012.

Please contact us with feedback and comments about this page. Created on 08 Nov 2012 - 14:14.

New Building Construction: Progress Update 28

General

Cranes & Hoist:- Cladding units on the north block and will continue with reconstituted stone fins using tower crane TC2. The south block will be served with tower crane TC1 and will be supplemented with a small “city crane”.

Sample Rooms:- Three “early” office rooms have had the walls skimmed with plaster, the raised floor installed and under floor activities started.

Future works for October

Architectural Metalwork:- The steel frame balustrade to the south major atrium is now largely installed and is continuing in the south minor atrium.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- The perimeter to roofs on the north block are complete. Stair core roofs and ground floor waterproofing will continue through to Christmas.

Cladding:- The units on the north block are targeted to be substantially complete by w.c. 5/112012 and have most of the corners etc complete by w.c. 12/11/2012. The south block after a slow start has made good progress and is on programme for the planned start for the fitout of areas E&F on 14/11/2012.

Glass Atrium Roofs:- The north atrium gridwork for glass installation is in progress and is targeting to be substantially complete by w.c.12/11/2012. The south block is continuing with scaffolding to the south major atrium. Early November will see the start of steel installation.

Reconstituted Stone:- Techrete commenced on site on 30/10/2012 with the south flank walls and will follow with installing the stone fins that surround the windows on the north.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to be complete by early December. The passenger lift to the south has the safety gates installed ready to progress.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. The ground source heat pump contractor have returned to carry out plantroom installations. Transformers and switchgear have been positioned as well as pipe racks to the basement.

Internal Fitout:- The second side of the plasterboard to the walls has commenced ahead of programme following the services within the walls. The raised floor is due to commence on 12/11/2012 to the first area of the north block.

Studwork and plasterboard walls have commenced on the large lecture theatre.

Recent Site Photos

[bg|new-building/site-visits/20121101|0]
Please contact us with feedback and comments about this page. Created on 05 Nov 2012 - 15:00.

Maths email service unavailable, Fri 2 Nov 22:00 GMT - completed

The Maths email service will be undergoing maintenance work on
Friday 2 November, from 22:00 GMT.

This work has now been completed.

If you use the web interface to access your email account, you will notice that the default colour scheme and style has changed due to the upgrade.  Users who access their mail through other means should not notice any change.

If you have any questions, please send an email to:

  @email

Please contact us with feedback and comments about this page. Created on 30 Oct 2012 - 14:05.

New Building Construction: Progress Update 27

General

Cranes & Hoist:- Tower Crane TC2 has been dedicated to serving the cladding units on the North Block and will continue with reconstituted stone fins. Tower crane TC1 has been serving the South Block and will be supplemented with a small “city crane”. The last remaining service units will also be lowered to the basement and mezzanine levels through holes left in the concrete slabs by the cranes.

Visits:- The Mathematics Department tour took place on the 12/10/2012.

Future works for October

Architectural Metalwork:- The steel frame balustrade to the south major atrium is installed to the 1st & 2nd floors and will continue to the remaining floors.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- Perimeter to roofs, stair core roofs and ground floor waterproofing will continue through to Christmas.

Cladding:- The units on the north block have been largely installed to three sides of the building. The south has units installed on the south elevation and will now continue on the west elevation.

Glass Atrium Roofs:- The North atrium steelwork is progressing which will shortly be followed by the glass installation w.c. 22/10/2012. The south minor atrium has received a high level scaffold. The South major atrium has had the had the ground floor “crystal” hole temporarily covered and will continue with a high level scaffold in the next few weeks.

Ceiling insulation:- Plasterboard contractor CG Reynolds have completing the basement ceiling insulation in the north and south buildings, and are progressing on the 1st and 2nd floors with plasterboard. Head track (C shaped metal angle) has been fixed to many soffits delignating the room layouts. Lecture Theatre main walls are expected to commence w.c 22/10/2012.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north commenced on 5/10/12.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement and have commenced drainage, sprinklers and containment on the mezzanine level. Service modules are largely installed now that the ceiling insulation has been fixed into place. (A service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces). Conduits which will contain wiring for lights and switches continue being fixed to the stair cores.

Recent Site Photos

[bg|new-building/site-visits/20121019|0]
Please contact us with feedback and comments about this page. Created on 19 Oct 2012 - 14:18.

Marcus du Sautoy to Present the Queen with a Symmetrical Object in Hyperspace

Marcus du Sautoy has discovered some significant new symmetrical objects but they currently have no names. Marcus has invited members of the public to name some of these shapes in return for a donation to charity. Each curve is defined by four numbers, three chosen by the individual and one chosen by the system.

 

Marcus has chosen a set of three numbers with particular significance to the Diamond Jubilee - 1952, the year of The Queen's accession to the throne, 2012, and 60 (the years she has reigned) - and named the corresponding symetrical object The Diamond Jubilee Group. He will present a certificate for The Diamond Jubilee Group to the Queen.

 


For further information see

Please contact us with feedback and comments about this page. Created on 13 Oct 2012 - 09:27.

New Building Construction: Progress Update 26

General

Cranes & Hoist:- Now that the structure is complete the cranes will predominantly be utilised for the installation of cladding panels. The remaining service units will also be lowered to the basement and mezzanine levels through holes left in the concrete slabs by the cranes. The hoist has been removed now that the bulk of the blockwork is complete.

Future works for October

Steel Bridge, Stair & Columns:- All stairs and bridges above ground level are now installed. The steel frame balustrade to the north block is virtually complete, while the south major atrium has steel frame balustrade to the 1st floor.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Structure:- The last major concrete pour was carried out on 20/9/2012. Tables have now been struck following the concreting of the roof upstands.

Waterproofing & Flat Roof:- The ground floor perimeter of the building has been largely waterproofed, with insulation and firm topping laid on the north block on the south side. The area on the south block south side is also in preparation for cladding to start.

Cladding:- The units on the north block have been erected adjacent to the Woodstock Road and are largely complete to the north elevation. The south has commenced with the installation of brackets adjacent to Somerville College.

Glass Atrium Roofs:- The North atrium steelwork is progressing which will shortly be followed by the glass installation. The south atriums are now ready to receive a high level scaffold before steelwork operations begin.

Ceiling insulation:- Plasterboard contractor CG Reynolds are completing the basement ceiling insulation in the north and south buildings, and are progressing on the 1st and 2nd floors with metal studwork.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north commenced on 5/10/2012.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage, sprinklers and ductwork at the basement and are commenced drainage and sprinklers on the mezzanine level. Service modules are largely installed now that the ceiling insulation has been fixed into place. (A service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces). Conduits which will contain wiring for lights and switches are being fixed to the stair cores.

Recent Site Photos

[bg|new-building/site-visits/20121004|0]
Please contact us with feedback and comments about this page. Created on 05 Oct 2012 - 11:53.

Success for Oxford at SET Awards

Congratulations to Oxford student Jo French, who has won not only the Mathematics category but also the overall Student of the Year category at the SET Awards ceremony. The prize was for her project on Differential Operators on Base Affine Space. Her project supervisor, Kobi Kremnitzer, was thereby named Best Lecturer. There were more than 500 entries from more than 100 universities.

Please contact us with feedback and comments about this page. Created on 28 Sep 2012 - 07:59.

New Building Construction: Progress Update 25

General

Cranes & Hoist:- The service modules (pre-assembled pipes, ducts and wire trays on a metal frame) continue to be delivered, before carefully being lowered by crane through an access hole into the lower floors. This will be followed by plant deliveries.

Visits:- The Mathematics Department tour took place on the 14/92012.

Future works for September

Steel Bridge, Stair & Columns:- A scaffold mounted on a rail system has been erected now that the steel staircases in the north building have been installed in the atrium. All steel bridges have been fixed into position in the south minor and south major atriums. This will followed in w.c. 24/9/2012 with the remaining steel above ground stair installation.

Blockwork:- Perimeter walls in the basement and mezzanine are complete leaving a number of walls to service rooms to complete.

4th Floor:- The remaining pour on the south was concreted on 7/9/2012. These slabs consist of a set of precast concrete planks (temporary supported) with an insitu concrete topping with strands (steels within tubes) which are stressed (tightened at the ends) after the concrete has set hard.

5th Level Roof:- The roof is expected to be complete towards the end of September, the last major pour was completed on 20/9/2012.

Waterproofing & Flat Roof:- The ground floor perimeter of the building has been largely waterproofed, with insulation and firm topping laid on the north block on the south side. The area on the south block south side is also in preparation for cladding to start.

Cladding:- The units on the north block have been erected adjacent to the Woodstock Road and are progressing along the north elevation for the first two levels (half of elevation). The south is expected to start in the coming weeks.

Ceiling insulation:- Plasterboard contractor CG Reynolds have continued with basement ceiling insulation in the north and south buildings, and are now progressing on the 1st floor with metal studwork.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to start by October.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage at the basement and mezzanine levels. Ductwork & sprinklers have also commenced in the north and service modules continue to be lifted and fixed in the ceiling of the basement. (a service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces).