New Building News

New Building Construction: Progress Update 32

Future works for January

Architectural Metalwork:- Entrance feature stair is installed together with the main elements of the basement staircases.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- 3rd & 4th Level main roof to the north has been waterproofed while the south has had the 4th level part waterproofed.

Cladding:- The north block is complete. All elevations to the south block have commenced with mainly corner sections to complete.

Glass Atrium Roofs:- The north atrium roof is largely enclosed. The south minor atrium main support beams and gridwork are in place with glass substantially installed. South major atrium has main support beams substantially installed, with temporary cover forming a “tent” over the middle area.

Reconstituted Stone:- The Stone contractor Techrete are progressing on the north and south blocks with the stone fins that surround the windows, with a priority to those above the Entrance.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift to the south has commenced and is expected to be complete in January. The 2nd car lift is expected to take 7 weeks.

Mechanical & Electrical:- The majority of plant has been delivered including the generator. Services contractor Crownhouse have largely installed internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. Cabling and wiring are ongoing in the coming weeks.

Internal Fitout:- All zones have commenced on the north while 5 out of 8 zones have commenced on the south. Door Frames have recently commenced in the North.

Joinery:- Carcass works for balustrading within the at South Atrium have commenced and the carcass is virtually complete in the north.

Smoke Curtains:- Carcass works for smoke curtains are expected in January. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

Recent Site Photos

New Building Construction: Progress Update 31

General

Cranes & Fork Lifts:- Tower Crane TC2 is being used to secure the reconstituted stone fins. The south block is served with tower crane TC1 and will be supplemented occasionally with a small “city crane” and a roof “spider” crane . Internal materials are largely served by a fork lift and with use of the tower crane when required.

Sample Rooms:- 3 “early” office rooms are now largely complete ready for sample furniture in the new year

Visits:- The Mathematics Department tour took place on the 7/12/2012.

Future works for January

Architectural Metalwork:- Basement staircases (3 No) have commenced as has the feature stair at the Entrance.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- 3rd Level main roof to the north has been waterproofed and are now progressing to the 4th and 5th level roofs.

Cladding:- The north block is almost complete. All elevations to the south block have commenced with mainly corner sections to complete. The bulk of units will be installed by Christmas.

Glass Atrium Roofs:- The north atrium roof is largely enclosed. The south minor atrium main support beams are installed and the gridwork for glass has commenced. South major atrium has main support beams substantially installed.

Reconstituted Stone:- The Stone contractor Techrete are progressing on the north block with the stone fins that surround the windows.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to be complete by Christmas. The passenger lift to the south has commenced and is expected to be complete in early January. The 2nd car lift is expected to take 7 weeks.

Mechanical & Electrical:- The majority of plant has been delivered except the generator which is due 17th December. Services contractor Crownhouse have largely installed internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. Cabling and wiring are ongoing in the coming weeks.

Internal Fitout:- All zones have commenced on the north while 4 out of 8 zones have commenced on the south.

Joinery:- Carcass works for balustrading within the at South Atrium have commenced and the carcass is virtually complete in the north.

Smoke Curtains:- Carcass works for smoke curtains are expected in January. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

Recent Site Photos

New Building Construction: Progress Update 30

General

Cranes & Fork Lifts:- Tower Crane TC2 is being used to secure the reconstituted stone fins. The south block is served with tower crane TC1 and will be supplemented occasionally with a small “city crane” and a roof “spider” crane . Internal materials are largely served by a fork lift and with use of the tower crane when required.

Sample Rooms:- Three “early” office rooms are now virtually complete with carpet and finals being the last items installed.

Future works for December

Architectural Metalwork:- Three basement staircases are due by the end of the month and the entrance feature stair is targeted for 3/12/2012.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- Now that the perimeter to roofs are complete, the next areas will be the core 1 roof followed by 3rd level main roof works.

Cladding:- Corner units continue to be installed on the north block. All elevations to the south block have commenced. The bulk of units will be installed by Christmas.

Glass Atrium Roofs:- The north atrium roof is expected to be enclosed by 7/12/2012. The south minor atrium main support beams are installed and is ready for glass to be installed. South major atrium will continue to install main support beams.

Reconstituted Stone:- The Stone contractor Techrete are progressing on the north block with the stone fins that surround the windows.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to be complete by early December. The passenger lift to the south has commenced and is expected to be complete in early January.

Mechanical & Electrical:- The majority of plant has been delivered except the generator which is due mid December. Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine.

Internal Fitout:- Under floor services are ongoing generally 1 week ahead of programme on the north block. On the South block the first zones E&F have commenced on 12/11/2012 in line with programme.

Joinery:- Carcass works for balustrading within the North Atrium have commenced.

Smoke Curtains:- Carcass works for smoke curtains are expected in mid December. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

Recent Site Photos

New Building Construction: Progress Update 29

General

Cranes & Fork Lifts:- Tower Crane TC2 is being used to secure the reconstituted stone fins. The south block is served with tower crane TC1 and will be supplemented occasionally with a small “city crane” and a roof “spider” crane . Internal materials are largely served by a fork lift and with use of the tower crane when required.

Sample Rooms:- Three “early” office rooms are in progress with skirting, door frame and door installations followed shortly by service finals and carpet.

Visits:- The Mathematics Department tour took place on the 9/11/2012.

Future works for November

Architectural Metalwork:- After completion of the steel frame balustrade, the next installations will be the main entrance staircase and basement stairs due at the end of the month.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- The perimeter to roofs are continuing to the south block and core roofs.

Cladding:- Corner units continue to be installed on the north block. The south block continues along both east and west elevations and has also started on the NE elevation above the Entrance.

Glass Atrium Roofs:- The north atrium roof has the main area largely installed with glass. The south minor atrium has the main support beams installed, while south major is being drilled in readiness for steelwork.

Reconstituted Stone:- Techrete are progressing on the north block with the stone fins that surround the windows on the north.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to be complete by early December. The passenger lift to the south has the safety gates installed ready to install at the end of November.

Mechanical & Electrical:- The majority of plant has been delivered except the generator which is due imminently. Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine.

Internal Fitout:- Plasterboard walls are progress to all zones of the north block. The raised floor commence on 12/11/2012 to the first area of the north block 1 week ahead of programme. On the South block the first zones E&F have commenced on 12/11/2012 in line with programme.

Recent Site Photos

New Building Construction: Progress Update 28

General

Cranes & Hoist:- Cladding units on the north block and will continue with reconstituted stone fins using tower crane TC2. The south block will be served with tower crane TC1 and will be supplemented with a small “city crane”.

Sample Rooms:- Three “early” office rooms have had the walls skimmed with plaster, the raised floor installed and under floor activities started.

Future works for October

Architectural Metalwork:- The steel frame balustrade to the south major atrium is now largely installed and is continuing in the south minor atrium.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- The perimeter to roofs on the north block are complete. Stair core roofs and ground floor waterproofing will continue through to Christmas.

Cladding:- The units on the north block are targeted to be substantially complete by w.c. 5/112012 and have most of the corners etc complete by w.c. 12/11/2012. The south block after a slow start has made good progress and is on programme for the planned start for the fitout of areas E&F on 14/11/2012.

Glass Atrium Roofs:- The north atrium gridwork for glass installation is in progress and is targeting to be substantially complete by w.c.12/11/2012. The south block is continuing with scaffolding to the south major atrium. Early November will see the start of steel installation.

Reconstituted Stone:- Techrete commenced on site on 30/10/2012 with the south flank walls and will follow with installing the stone fins that surround the windows on the north.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to be complete by early December. The passenger lift to the south has the safety gates installed ready to progress.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. The ground source heat pump contractor have returned to carry out plantroom installations. Transformers and switchgear have been positioned as well as pipe racks to the basement.

Internal Fitout:- The second side of the plasterboard to the walls has commenced ahead of programme following the services within the walls. The raised floor is due to commence on 12/11/2012 to the first area of the north block.

Studwork and plasterboard walls have commenced on the large lecture theatre.

Recent Site Photos

New Building Construction: Progress Update 27

General

Cranes & Hoist:- Tower Crane TC2 has been dedicated to serving the cladding units on the North Block and will continue with reconstituted stone fins. Tower crane TC1 has been serving the South Block and will be supplemented with a small “city crane”. The last remaining service units will also be lowered to the basement and mezzanine levels through holes left in the concrete slabs by the cranes.

Visits:- The Mathematics Department tour took place on the 12/10/2012.

Future works for October

Architectural Metalwork:- The steel frame balustrade to the south major atrium is installed to the 1st & 2nd floors and will continue to the remaining floors.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Waterproofing & Flat Roof:- Perimeter to roofs, stair core roofs and ground floor waterproofing will continue through to Christmas.

Cladding:- The units on the north block have been largely installed to three sides of the building. The south has units installed on the south elevation and will now continue on the west elevation.

Glass Atrium Roofs:- The North atrium steelwork is progressing which will shortly be followed by the glass installation w.c. 22/10/2012. The south minor atrium has received a high level scaffold. The South major atrium has had the had the ground floor “crystal” hole temporarily covered and will continue with a high level scaffold in the next few weeks.

Ceiling insulation:- Plasterboard contractor CG Reynolds have completing the basement ceiling insulation in the north and south buildings, and are progressing on the 1st and 2nd floors with plasterboard. Head track (C shaped metal angle) has been fixed to many soffits delignating the room layouts. Lecture Theatre main walls are expected to commence w.c 22/10/2012.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north commenced on 5/10/12.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage, sprinklers, ductwork, pipework and containment at the basement and have commenced drainage, sprinklers and containment on the mezzanine level. Service modules are largely installed now that the ceiling insulation has been fixed into place. (A service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces). Conduits which will contain wiring for lights and switches continue being fixed to the stair cores.

Recent Site Photos

New Building Construction: Progress Update 26

General

Cranes & Hoist:- Now that the structure is complete the cranes will predominantly be utilised for the installation of cladding panels. The remaining service units will also be lowered to the basement and mezzanine levels through holes left in the concrete slabs by the cranes. The hoist has been removed now that the bulk of the blockwork is complete.

Future works for October

Steel Bridge, Stair & Columns:- All stairs and bridges above ground level are now installed. The steel frame balustrade to the north block is virtually complete, while the south major atrium has steel frame balustrade to the 1st floor.

Blockwork:- Largely finished with a number of walls to service rooms to complete.

Structure:- The last major concrete pour was carried out on 20/9/2012. Tables have now been struck following the concreting of the roof upstands.

Waterproofing & Flat Roof:- The ground floor perimeter of the building has been largely waterproofed, with insulation and firm topping laid on the north block on the south side. The area on the south block south side is also in preparation for cladding to start.

Cladding:- The units on the north block have been erected adjacent to the Woodstock Road and are largely complete to the north elevation. The south has commenced with the installation of brackets adjacent to Somerville College.

Glass Atrium Roofs:- The North atrium steelwork is progressing which will shortly be followed by the glass installation. The south atriums are now ready to receive a high level scaffold before steelwork operations begin.

Ceiling insulation:- Plasterboard contractor CG Reynolds are completing the basement ceiling insulation in the north and south buildings, and are progressing on the 1st and 2nd floors with metal studwork.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north commenced on 5/10/2012.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage, sprinklers and ductwork at the basement and are commenced drainage and sprinklers on the mezzanine level. Service modules are largely installed now that the ceiling insulation has been fixed into place. (A service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces). Conduits which will contain wiring for lights and switches are being fixed to the stair cores.

Recent Site Photos

New Building Construction: Progress Update 25

General

Cranes & Hoist:- The service modules (pre-assembled pipes, ducts and wire trays on a metal frame) continue to be delivered, before carefully being lowered by crane through an access hole into the lower floors. This will be followed by plant deliveries.

Visits:- The Mathematics Department tour took place on the 14/92012.

Future works for September

Steel Bridge, Stair & Columns:- A scaffold mounted on a rail system has been erected now that the steel staircases in the north building have been installed in the atrium. All steel bridges have been fixed into position in the south minor and south major atriums. This will followed in w.c. 24/9/2012 with the remaining steel above ground stair installation.

Blockwork:- Perimeter walls in the basement and mezzanine are complete leaving a number of walls to service rooms to complete.

4th Floor:- The remaining pour on the south was concreted on 7/9/2012. These slabs consist of a set of precast concrete planks (temporary supported) with an insitu concrete topping with strands (steels within tubes) which are stressed (tightened at the ends) after the concrete has set hard.

5th Level Roof:- The roof is expected to be complete towards the end of September, the last major pour was completed on 20/9/2012.

Waterproofing & Flat Roof:- The ground floor perimeter of the building has been largely waterproofed, with insulation and firm topping laid on the north block on the south side. The area on the south block south side is also in preparation for cladding to start.

Cladding:- The units on the north block have been erected adjacent to the Woodstock Road and are progressing along the north elevation for the first two levels (half of elevation). The south is expected to start in the coming weeks.

Ceiling insulation:- Plasterboard contractor CG Reynolds have continued with basement ceiling insulation in the north and south buildings, and are now progressing on the 1st floor with metal studwork.

Lifts:- The lift contractor Thyssen have completed the first car lift in the north. The passenger lift in the north is expected to start by October.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage at the basement and mezzanine levels. Ductwork & sprinklers have also commenced in the north and service modules continue to be lifted and fixed in the ceiling of the basement. (a service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces).

Recent Site Photos

New Building Construction: Progress Update 24

General

Cranes & Hoist:- The service modules (pre-assembled pipes, ducts and wire trays on a metal frame) continue to be delivered, before carefully being lowered by crane through an access hole into the lower floors. This will be followed by plant deliveries.

Visits:- On 31st August 2012 the University / building teams celebrated the last concrete to be placed on the north block with a Topping Out Ceremony. This involved concreting in to the roof a small piece of yew.

Future works for September

Steel Bridge, Stair & Columns:- Now that the steel staircases in north have been installed in the atrium the scaffold mounted on a rail system is being erected. The majority of steel bridges have been fixed into position in the south minor and south major atriums. The remaining 3rd floor bridge will be installed shortly together with staircases.

Blockwork:- Perimeter walls in the basement are complete and mezzanine will continue until mid September.

3rd Floor:- The remaining pour 34B on the south was concreted on 24/8/2012. These slabs consist of a set of precast concrete planks (temporary supported) with an insitu concrete topping with strands (steels within tubes) which are stressed (tightened at the ends) after the concrete has set hard.

4th Floor:- The remaining pour on the south is expected to be concreted on 7/9/2012.

5th Level Roof:- The roof is expected to be complete towards the end of September.

Waterproofing & Flat Roof:- Rock have almost waterproofed the ground floor perimeter of the building, allowing the insulation and firm topping to commence on the north block.

Cladding:- The first units have been erected adjacent to the Woodstock Road. The initial works have concentrated on the bracketry but will now focus on unit installation along two elevations.

Ceiling insulation:- Plasterboard contractor CG Reynolds have continued with basement ceiling insulation in the north and south buildings, and will now continue with walls installation.

Lifts:- The lift contractor Thyssen continues with the car lift in the north being the first installation. The passseger lift in the north is expected to start by October.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage at the basement level. Ductwork & sprinklers have also commenced in the north and service modules continue to be lifted and fixed in the ceiling of the basement. (a service module comprises of a light steel frame to which mainly pipework and containment have been fixed in the factory. These are then joined on site with connecting pieces).

Recent Site Photos

New Building Construction: Progress Update 23

General

Cranes & Hoist:- The service modules (pre-assembled pipes, ducts and wire trays on a metal frame) continue to be delivered, before carefully being lowered by crane through an access hole into the lower floors. This will be followed by plant deliveries.

North Building:- The main structure of the north building is now complete allowing the wall cladding and atrium roof to progress in this area.

Future works for September

Steel Bridge, Stair & Columns:- Remaining steel columns in the entrance have been installed. Steel bridges have been fixed into position in the south minor atrium and continue into the south major in the next month. Steel staircases in north have been installed in the atrium.

Blockwork:- Remaining perimeter walls in the basement and mezzanine will continue until mid September.

3rd Floor:- The remaining pour 34B on the south is expected to be concreted on 24/8/2012. All of the 3rd floor slabs will be complete before the end August.

4th Floor:- The 1st pour on the south was concreted on 16/8/2012. The last pour is expected to be poured in early September.

5th Level Roof:- The roof is expected to be complete towards the end of September.

Waterproofing & Flat Roof:- Rock have almost waterproofed the ground floor perimeter of the building, allowing the insulation and firm topping to commence.

Ceiling insulation:- Plasterboard contractor CG Reynolds have continued with basement ceiling insulation in the north and south buildings.

Lifts:- The lift contractor Thyssen continues with the car lift in the north being the first installation.

Mechanical & Electrical:- Services contractor Crownhouse continue with internal drainage from the north to the centre on the basement level. Ductwork & sprinklers have also commenced in the north and service modules have been lifted and fixed in the ceiling of the basement.

Recent Site Photos