New Building News

New Building Construction: Progress Update 2

Ongoing Works

Piling Rigs:-The piling activities are now complete and the rigs have been dismantled and transported off site.

Secant Piles:- In total there will have been 532 holes that were drilled, reinforced with steel and concreted to a depth generally in excess of 20m. Secant is a term in mathematics and comes from the Latin secare (to cut). Initially every other hole is drilled and concreted (female piles). These are followed shortly afterwards by drilling into the gaps and the relatively soft female concrete piles, before concreting the male piles. This will form a continuous concrete “wall” underground.

Pile Capping:- The tops of the concrete piles are exposed and are then cut to a more accurate height using a mechanical cropper and breakers. This operation is over half way around the building and will continue for the remainder of October.

Capping Beam:- A concrete capping beam is being constructed along the top of the piles to connect them and form a solid continuous ring beam. This operation has commenced near the Woodstock Road and will continue to the beginning of November.

Steel Propping:- Large steel props are largely installed to one end of the site. These will brace at ground level along the capping beam in order to restrain the ground pressure from the surrounding sides of the building while digging continues.

Gates:- Gate 5 adjacent to the St Lukes Chapel is now operational. Gate 7 remains the main access with Elliot Thomas guard in attendance.

Oxford Site Review:- The monthly department site review for October was carried out last week, showing the progress made to date.

Future works for October / November

The Big Dig:- Excavation of the soil within the footprint of the building has started ahead of programme and is expected to continue until Christmas 2011. There will be over 47,000m3 of soil to be removed. The gravel will be recycled and the clay used locally as fill material. As the excavation proceeds the props and capping beam will be closely monitored to ensure there is no movement.

Cleaning of Piles:- Once the excavation of the soil is sufficiently advanced in early November the exposed piles (concrete “wall” below ground level) will be cleaned and inspected.

New Building Construction: Progress Update 1

Ongoing Works

Piling Rigs:-The piling activities are now largely installed with drilling operations continuing for only one more week.

Secant Piles:- There is a total of 532 secant piles bored to a depth in excess of 20m to form a continuous concrete pile wall around the perimeter of the double storey basement. There are two types of secant pile: a female pile formed from a weaker concrete mix and a male pile that is reinforced with steel and provides the strength in the wall. Secant is a mathematical term and comes from the Latin secare (to cut). The male pile cuts into the female pile providing a continuous sealed basement wall.

Pile Cropping:- It is necessary to cut down the top of the piles to expose the reinforcement cage to tie into the capping beam and also remove any debris that sometimes contaminates the top of the pile when extracting the auger. This activity is carried out using a specialist cropping attachment for the excavator and trimmed using breakers. We are currently 50% through this activity and expect to complete towards the end of October.

Capping Beam:- A concrete capping beam is being constructed along the top of the piles to connect them and form a solid continuous ring beam. This operation has commenced near the Woodstock Road and will continue to the beginning of November.

Future works for October

Steel Propping:- Large steel props are expected to be secured into position on w/c 10-10-11 using a crane. These will brace at ground level along the capping beam in order to restrain the ground pressure from the surrounding sides of the building once digging commences.

The Big Dig:- Excavation of the soil within the footprint of the building is expected to start in mid October. There will be over 47,000m3 of soil to be removed. The gravel will be recycled and the clay used locally as fill material. As the excavation proceeds the props and capping beam will be closely monitored to ensure there is no movement.

Images from Site Tour on 14/10/2011

Construction of the New Maths Building Officially Begins

A ground breaking ceremony was held at noon on 2nd August 2011 to mark the official beginning of the construction phase for the new maths building.

See the new building section of the website for more information on the project including pictures showing how the building will look and time lapse movies showing recent activity on site.

Final Stage Approval of the Mathematical Institute New Building by the University Council

We are delighted to report the recent final stage approval of the Mathematical Institute new building by the University Council. With this approval, construction is set to commence later this summer with a projected two year build timeline. We plan to be settled in to the new building for the beginning of the 2013-14 academic year.

However, this does not mean that work to secure funding will cease. We aim to raise another £19.3M in addition to the £10.1M which has been raised to date. This will ensure that the department enters the new building in a good financial position, fully able to make the best use of the new, inspiring environment. We look forward to providing you with news and updates on the building as work progresses.

Syndicate content