General

Position:- The project remains 1 week ahead of programme due to the more critical concrete pours that were advanced.

Curtain Walling Mock Up:- A mock up of the curtain walling will be erected on site in the near future.

Balustrade: Following the review of the mock up a decision has been made to now move forward with this element.

Precast Stairs: Precast stairs have started to be delivered in readiness for installation to the relevant areas.

Considerate Contractors Scheme:- CCS visited the site on 16/2/2012 and gave a positive report scoring 38/40.

Future works for March

GSHP:- The pipes that were sunk at the start of the project continue to be cropped and joined to header connection pipes that will terminate in access ducts in the plant rooms. The works are now focused in the last areas onsite working towards the corner of the central area. This is expected to be complete in the next 2 weeks.

Drainage & Basement Slab:- The more complex basement pours (3A) adjacent to the lower plantroom in the south have been largely poured. It is targeted to have all the south basement complete by the beginning of March.

Steel Beams & Columns:- Holding down bolts are fixed accurately to the formwork / reinforcement in order that steel I beams and columns can be bolted to the structure after the slab is poured. The steel column and beams are expected to be onsite week commencing 5/3/2012.

Plant Room & Services:- The service trenches to the centre have largely been excavated now that the bulk dig removal has finished. The lower level plant room walls in the south have been formed with steel reinforcement in readiness for a concrete pour.

Mezzanine Floor:- Pour No 8 on the mezzanine level of the north has been poured and core 1 twin walls have been erected. The formwork has also started on the south in one corner.