Position:- The project is 1 week ahead of programme with the more critical activities running through the south.

Curtain Walling Mock Up:- The curtain walling mock up is in progress and is expected to be complete by Easter.

Visits:- The Maths Department visited the site on 30/3/2012 to view the latest progress.

Future works for April

Drainage & Basement Slab:- The central basement slab (5B) was poured on 30/3/2012. The remaining two pours in the basement will now follow including the last core 3 area. It is targeted to have all the central basement complete by mid April.

Steel Beams & Columns:- The steelwork over the lower plant room was installed on 26/3/2012. The double height steel columns that support steel beams over the small lecture theatre have also been installed. Holding down bolts are fixed accurately to the formwork / reinforcement in order that steel I beams and columns can be bolted to the structure after the slab is poured.

Plant Room & Services:- The service trenches to the centre have commenced now that the bulk dig removal has finished.

Mezzanine Floor:- The mezzanine level pour 9 was poured on 5/4/2012 in the south with following pours progressively moving towards the NW corner.

Ground Floor:- The second main ground floor slab (16B) has been poured in the north on 4/4/2012. As the slabs are completed and gain strength the temporary large yellow props spanning across the site will progressively be removed. To the south the first main slab (13D) was poured on 3/4/2012.

1st Floor:- The initial slab to the 1st floor is expected to be poured after Easter in w.c. 13/4/2012. These slabs consist of a set of precast concrete planks (temporary supported) with an insitu concrete topping with strands (steels within tubes) which are stressed (tightened at the ends) after the concrete has set hard.

Recent Site Photos

[bg|new-building/site-visits/20120405|0]
Please contact us with feedback and comments about this page. Created on 07 Apr 2012 - 16:10.