General

Cranes & Folk Lifts:- An occasional mobile crane will be brought in when required (incl. w.c. 29/7/2013).

Entrance:- The pedestrian and vehicle entrance has been moved from Gate 7 to the rear on Walton Street whilst final tarmac operations are carried out along the main access road.

Familiarisation:- A timetable at the end of July is in progress for system familiarisation.

Visits:- The final monthly Department tour took place on 19/7/2013.

Future works for July/August

Entrance:- Remaining final finishes to conclude.

Cladding:- Units left out for access (including crystal glass) have now been closed up.

Glass Atrium Roofs:- Complete with snagging ongoing.

Reconstituted Stone & Brise Soleil:- External Brise Soleil installations (louvred sun shade) are complete.

Ground Crystals: Mainly installed with remaining finishes to complete.

Architectural Metalwork:- Roof terrace balustrade glass is ongoing.

Waterproofing & Flat Roof:- Decking will follow balustrading.

Lifts:- The lift contractor Thyssen have installed all large lifts. Two platform lifts give access to the large and medium theatres and a stage lift to the large lecture theatre will give access to the stage.

Mechanical & Electrical:- Commissioning is ongoing that will test and balance each system.

Internal Fitout:- The north block is being desnagged. The south building is continuing upper level finals with furniture and shelving installation following closely behind.

Lecture Theatres:- All lecture theatres are largely installed with remaining finals to complete.

Joinery:- Timber balustrade panels installed to the south major atrium with finals to complete.

Smoke Curtains:- Smoke curtains have been installed in both the north & south atriums and entrance, with commissioning to complete. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Tarmac works are in progress along the main entrance road. Penrose paving is ongoing. Kerb laying and paving will now focus on remaining works to Gate 5.

Basement:- Largely finished with minor works to complete.

Inspections:- As areas become complete, sections are made available for inspections.

Recent Site Photos

[bg|new-building/site-visits/20130726|0]
Please contact us with feedback and comments about this page. Created on 26 Jul 2013 - 14:35.