Cranes & Folk Lifts:- Fork lifts will assist with final clear away tasks.

Entrance:- The Gate 7 access has been reopened to vehicles and segregated pedestrian path.

Recent Works

Entrance:- Remaining final finishes.

Cladding:- Units left out for access (including crystal glass) have now been closed up.

Glass Atrium Roofs:- Complete with snagging.

Reconstituted Stone & Brise Soleil:- External Brise Soleil installations (louvred sun shade) are complete.

Ground Crystals: Complete with snagging.

Architectural Metalwork:- Hand in area posts. Column casings.

Waterproofing & Flat Roof:- Decking. Sedum replanting.

Mechanical & Electrical:- Commissioning has tested and balanced each system.

Internal Fitout:- North block snagging. The south building has had cleaning activities and final finishes being closed out.

Lecture Theatres:- All lecture theatres are largely installed.

Joinery:- Final finishes and snagging

External Works:- The main entrance road has been tarmaced with barriers. Penrose paving is ongoing. Gate 5 pavement crossover will be carried out once OCC permission has been granted.

Basement:- Largely finished.

Inspections:- As areas become complete, sections are being made available for inspections.