Cranes & Folk Lifts:- Fork lifts will assist with final clear away tasks.
Entrance:- The Gate 7 access has been reopened to vehicles and segregated pedestrian path.
Recent Works
Entrance:- Remaining final finishes.
Cladding:- Units left out for access (including crystal glass) have now been closed up.
Glass Atrium Roofs:- Complete with snagging.
Reconstituted Stone & Brise Soleil:- External Brise Soleil installations (louvred sun shade) are complete.
Ground Crystals: Complete with snagging.
Architectural Metalwork:- Hand in area posts. Column casings.
Waterproofing & Flat Roof:- Decking. Sedum replanting.
Mechanical & Electrical:- Commissioning has tested and balanced each system.
Internal Fitout:- North block snagging. The south building has had cleaning activities and final finishes being closed out.
Lecture Theatres:- All lecture theatres are largely installed.
Joinery:- Final finishes and snagging
External Works:- The main entrance road has been tarmaced with barriers. Penrose paving is ongoing. Gate 5 pavement crossover will be carried out once OCC permission has been granted.
Basement:- Largely finished.
Inspections:- As areas become complete, sections are being made available for inspections.