New Building Construction: Progress Update 5

Ongoing Works
Steel Propping:- Large steel props are largely installed to the north and south of the site. These brace at ground level along the capping beam in order to restrain the ground pressure from the surrounding sides of the building while digging continues.
The Big Dig:- Excavation of the soil within the footprint of the building started ahead of programme and is expected to continue until Christmas 2011. There will be over 47,000m3 of soil to be removed. The gravel will be recycled and the clay used locally as fill material. As the excavation proceeds the props and capping beam will be closely monitored to ensure there is no movement.
Cleaning of Piles:- As piles continue to be exposed piles (concrete “wall” below ground level) they are being cleaned and inspected.
Future works for December
The Big Dig:- The excavation overall is now just over two thirds complete. The north is down to the correct level, the south will have another week for main dig excavation, and the central section will continue into the new year. The removal of soil will change from loading the lorries at the base of the ramps to loading from ground level as the excavation diminishes.
GSHP:- The pipes that were sunk at the start of the project will now be cropped and joined to header connection pipes that will terminate in access ducts in the plant rooms. The 1st section of the north is complete and the 2nd section of the north is due on Tuesday 6/12/2011. The south will then be progressed from Wednesday 7/12/2011.
Drainage & Slab:- By mid December the drainage will be ongoing and the 1st basement slab will be formed in the north of the site.
Hoarding:- Hoarding works adjacent to the main access road is continuing towards Gate 7 and is expected to be complete by 5/12/2011.
Tower Cranes:- Crane bases are concreted. The 1st tower crane is planned to be erected by use of a mobile crane on the weekend of 7th and 8th January 2012.
Recent Site Photos
| [bg|new-building/site-visits/20111201] |
Pile Capping:- The tops of the concrete piles are exposed and are then cut to a more accurate height using a mechanical cropper and breakers. This operation is now complete.
The Big Dig:- Excavation of the soil within the footprint of the building has started ahead of programme and is expected to continue until Christmas 2011. There will be over 47,000m3 of soil to be removed. The gravel will be recycled and the clay used locally as fill material. As the excavation proceeds the props and capping beam will be closely monitored to ensure there is no movement.
Secant Piles:- In total there have been 532 holes that were drilled, reinforced with steel and concreted to a depth generally in excess of 20m. These piles are now being cleaned down as the excavation progresses.
Piling Rigs:-The piling activities are now complete and the rigs have been dismantled and transported off site.
The Big Dig:- Excavation of the soil within the footprint of the building has started ahead of programme and is expected to continue until Christmas 2011. There will be over 47,000m3 of soil to be removed. The gravel will be recycled and the clay used locally as fill material. As the excavation proceeds the props and capping beam will be closely monitored to ensure there is no movement.
Piling Rigs:-The piling activities are now largely installed with drilling operations continuing for only one more week.
Steel Propping:- Large steel props are expected to be secured into position on w/c 10-10-11 using a crane. These will brace at ground level along the capping beam in order to restrain the ground pressure from the surrounding sides of the building once digging commences.