New Building Construction: Progress Update 43

General

Cranes & Fork Lifts:- Mobile cranes are being used occasionally when required.

Entrance:- The proposed closure of the access road from gate 7 with alternative access for a period of 9 days has been postponed to co-ordinate with neighbour/client requests. When a suitable time is established it will enable the final road build up to progress.

Familiarisation:- A timetable at the end of July has be proposed for system familiarisation.

Elliott Thomas Logistics: - Art Gallery in the Old chapel. Walk ways and roads being kept clean and tidy on a daily basis, Traffic management of construction vehicles and safe access for pedestrians/ cyclists and dust control by bringing a road sweeper to site.

Future works for June

Entrance:- Glass to main entrance is largely in and continuing with connections to guttering.

Cladding:- Units left out for access (especially crystal glass) will be closed up over the next few weeks.

Glass Atrium Roofs:- The north atrium roof is complete. The southern atriums have been glazed, with flashings and edge details to finish.

Reconstituted Stone & Brise Soleil:- Brise Soleil (louvred sun shade) is virtually complete.

Ground Floor Crystals: Glass to the crystals substantially complete and will now concentrate on closing the sides.

Architectural Metalwork:- Roof terrace balustrade brackets are now ready to receive glass.

Waterproofing & Flat Roof:- Decking followed by glass balustrading are due to commence.

Lifts:- The lift contractor Thyssen have installed all large lifts. 2 No platform are also installed. A stage lift will be incorporated into the large lecture theatre.

Mechanical & Electrical:- Commissioning is ongoing that will test and balance each system.

Internal Fitout:- Following carpets the north block is now being cleaned with shelving being added to offices shortly before furniture delivery.

Lecture Theatres:- Now that the staging and tiering are complete, the floor services and carpeting have followed and seating installed to the large lecture theatre. The tiling to the main mezzanine area continues.

Joinery:- Timber balustrade panels continue in the south major atrium.

Smoke Curtains:- Smoke curtain boxes have been installed in the north and south atriums. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Kerb laying and paving have been progressing to all external areas.

Basement:- Floor painting activities will follow preparation of basement areas.

Inspections:- As areas become complete, sections are made available for inspections.

Recent Site Photos

[bg|new-building/site-visits/20130613|0]
Please contact us with feedback and comments about this page. Created on 14 Jun 2013 - 09:41.

MPLS Teaching Awards for Fernando Alday, Philip Maini and Greg Gyurko

Congratulations to three members of the Mathematical Institute who were recognised in the 2013 Teaching Awards exercise, held across the Mathematical, Physical and Life Sciences Division. Fernando Alday and Philip Maini won two of the four Individual Awards for their outstanding contribution to undergraduate and graduate teaching respectively, and Greg Gyurko won the Special Category Award for Support Staff.

Please contact us with feedback and comments about this page. Created on 14 Jun 2013 - 08:49.

Prof. Roger Penrose discusses Relativity on Radio 4's 'In Our Time'

Roger Penrose, Emeritus Rouse Ball Professor of Mathematics at the University of Oxford, joins Astromer Royal Prof. Martin Rees and Ruth Gregory, Professor of Mathematics and Physics at Durham University to discuss one of the major scientific and intellectual achievements of any century.

Please contact us with feedback and comments about this page. Created on 13 Jun 2013 - 12:36.

New Building Construction: Progress Update 42

General

Cranes & Fork Lifts:- Mobile cranes are being used occasionally when required.

Entrance:- It is proposed that the access road from gate 7 will be closed with alternative access for a period of 9 days starting from either 8/6/2013 or 15/6/2013. This is to enable the final road build up to be progressed.

Familiarisation:- A timetable has been proposed for system familiarisation.

Visits:- The Mathematics Department tour took place on the 24/5/2013.

Future works for June

Architectural Metalwork:- Roof terrace balustrade brackets are now ready to receive glass.

Waterproofing & Flat Roof:- Decking followed by glass balustrading are due to commence.

Entrance:- The glass to the main roof area has been installed, and work will continue to glaze the sides.

Cladding:- Cladding units to both north and south are virtually installed apart from those left out for access.

Glass Atrium Roofs:- The north atrium roof is complete. The southern atriums have been glazed, with flashings and edge details to finish.

Reconstituted Stone & Brise Soleil:- Brise Soleil (louvred sun shade) is virtually complete.

Ground Crystals: The glass support steelwork to the north & south crystals are complete and ready for glass installation.

Lifts:- The lift contractor Thyssen have installed all large lifts. 2 platform lifts are presently being installed.

Mechanical & Electrical:- The power, water and gas are now connected. Commissioning has commenced and will test and balance each system.

Internal Fitout:- Carpet have been continuing in the north, while decorations and joinery are continuing in the south.

Lecture Theatres:- The staging and tiering are now close to completion, allowing floor services to progress. The tiling to the main mezzanine area has been installed under the north crystal area.

Joinery:- Specific timber balustrade panels have been completed in the south major atrium to allow the south crystal to be installed. The remaining less critical timber balustrade will now continue.

Smoke Curtains:- Smoke curtain boxes have been installed in the north and south atriums. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Kerb laying and paving have been progressing to all external areas.

Inspections:- As areas become complete, sections are made available for inspections.

Recent Site Photos

[bg|new-building/site-visits/20130530|0]
Please contact us with feedback and comments about this page. Created on 31 May 2013 - 09:32.

Mathematics Oxford Sculpture Competition: the shortlist

We were very pleased to receive over 160 applications to our Sculpture Competition, containing many excellent ideas and beautiful designs.

The Selection Committee has reviewed all the entries, and selected four proposals for further consideration. The shortlisted artists are

Please contact us with feedback and comments about this page. Created on 30 May 2013 - 11:43.

Facing the Challenge of the Puzzle Museum

Garden Party Image

The department recently sent a select group to James Dalgety’s wonderful Puzzle Museum, home to 50,000+ examples of the capacity of objects to challenge our imagination and ingenuity, with the aim of identifying puzzles that could form an exhibit to mark the opening of the new Mathematical Institute building.

[file:Trip_to_James_Dalgetys_wonderful_Puzzle_Museum.pdf=Read more about this visit in this account by Thomas Woolley]

Please contact us with feedback and comments about this page. Created on 24 May 2013 - 18:57.

New Building Construction: Progress Update 41

General

Cranes & Fork Lifts:- Mobile cranes are being used occasionally when required. The metal hoarding along the site access road will gradually be substituted with A shaped bases and harris fencing as greater access is required.

Future works for May

Architectural Metalwork:- Roof access ladders have been installed. Roof terrace balustrade brackets are now ready to receive glass. Stair balustrading are largely installed to core areas.

Waterproofing & Flat Roof:- Decking followed by glass balustrading are due to commence imminently.

Entrance:- The glass to the main roof area has been largely installed, and will now continue to glaze the sides.

Cladding:- Cladding units to both north and south are virtually installed apart from those left out for access.

Glass Atrium Roofs:- The north atrium roof is complete. The southern atriums have been glazed, with flashings and edge details to finish.

Reconstituted Stone & Brise Soleil:- Brise Soleil (louvred sun shade) is nearing completion.

Ground Crystals: The glass supports to the north crystals are complete and ready for glass installation. The south crystal steelwork is largely installed.

Lifts:- The lift contractor Thyssen will have the car lift and energy lift complete and tested by 17/5/2013.

Mechanical & Electrical:- The power, water and gas are now connected. Commissioning has commenced and will test and balance each system.

Internal Fitout:- Carpet have been continuing in the north, while decorations and joinery are continuing in the south.

Lecture Theatres:- The staging and tiering is complete to the large lecture theatre. The medium and small lecture theatres ceilings have progressed enough to allow both birdcage scaffolds to be removed and staging to start in the medium theatre. The tiling to the main mezzanine area has been installed under the north crystal area.

Joinery:- Specific timber balustrade panels have been completed in the south major atrium to allow the south crystal to be installed. The remaining less critical timber balustrade will now continue.

Smoke Curtains:- Smoke curtain boxes have been installed in the north and south minor atria. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Kerb laying and paving started on 29/4/2013. Four of the five external areas have commenced with either kerbs or paving.

Recent Site Photos

[bg|new-building/site-visits/20130516|0]
Please contact us with feedback and comments about this page. Created on 18 May 2013 - 15:14.