New Building Project Wins Gold CCS Award

Mathematical Institute project gold award and also a runners-up award for the Most Considerate Site 2013
Award collected on behalf of the team by Mick Sheehan, Steve Hollands and Phil Larkin from Laing O'Rourke, Richard Todd from PDCM and Keith Gillow from the Mathematical Institute.

At a Considerate Constructors Scheme's National Site Awards ceremony yesterday the Mathematical Institute project received a gold award and also a runners-up award for the Most Considerate Site 2013. This places the Mathematical Institute project within the top 25 in the country out of approximately 8000 in total. The award was collected on behalf of the team by Mick Sheehan, Steve Hollands and Phil Larkin from Laing O'Rourke, Richard Todd from PDCM and Keith Gillow from the Mathematical Institute. The preceeding day the neighbouring Radcliffe Infirmary refurbishment project also won a gold award and a runners-up award for Most Considerate Site 2013.

Please contact us with feedback and comments about this page. Created on 25 Apr 2013 - 19:46.

New Building Construction: Progress Update 39

General

Cranes & Fork Lifts:- TC1 tower crane is now planned to be dismantled on the 25th & 26th April. Any remaining works will then be carried out with the use of roof cranes or mobile cranes. The metal hoarding along the site access road will gradually be substituted with A shaped bases and harris fencing as greater access is required.

Visits:- The Mathematics Department tour took place on the 5/4/2013.

Future works for April

Architectural Metalwork:- External grille vents are expected to be delivered wc 26/4/2013. Roof terrace balustrade brackets continue to be installed. Stair balustrading are largely installed to core areas.

Waterproofing & Flat Roof:- All roofs have been waterproofed and largely paved where required. Sedum (green roof) planting is planned to commence in April.

Entrance:- Following the installation of the long main beams, gridwork is nearing completion ready for glass installations.

Cladding:- Cladding units to both north and south are virtually installed apart from those left out for access.

Glass Atrium Roofs:- The north atrium roof is complete. The southern atriums have the majority of glass installed, with flashings and edge details to finish.

Reconstituted Stone & Brise Soleil:- The Stone contractor Techrete are largely complete on the north and are 95% on the south block with the stone fins that surround the windows. Brise Soleil is following working on the south block.

Ground Crystals: The glass supports to the north crystals have commenced.

Lifts:- The lift contractor Thyssen have completed both car lifts & both passenger lifts, and is almost complete on the goods lift .

Mechanical & Electrical:- The power, water and gas are now connected. Commissioning has commenced and will test and balance each system.

Internal Fitout:- All zones have commenced on the north and south buildings. Final service fittings are continuing in the north, while door installation and decoration are continuing in the south. The birdcage scaffold has been removed from the large lecture theatre allowing the staging and tiering to commence.

Joinery:- Timber balustrade panels have started in the south major atrium.

Smoke Curtains:- Smoke curtain boxes have been installed in the north. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- The crane base has been broken up and removed. Kerb laying and paving is due to start on 29/4/2013.

Recent Site Photos

[bg|new-building/site-visits/20130418|0]
Please contact us with feedback and comments about this page. Created on 19 Apr 2013 - 16:41.

New Building Construction: Progress Update 38

General

Cranes & Fork Lifts:- TC1 tower crane is planned to be dismantled on the 17th & 18th April. Any remaining works will then be carried out with the use of roof cranes or mobile cranes. The metal hoarding along the site access road will gradually be substituted with A shaped bases and harris fencing as greater access is required.

Entrance:- The pedestrian entrance has been moved from Gate 1 to Gate 7 while services are being installed adjacent to Somerville College.

Future works for April

Architectural Metalwork:- External grille vents are expected to be delivered wc 26/4/2013. Roof terrace balustrade brackets continue to be installed. Stair balustrading are largely installed to core areas.

Waterproofing & Flat Roof:- All roofs have been waterproofed and largely paved where required. Sedum (green roof) planting is planned to commence in April.

Entrance:- All the long main beams have been installed and the gridwork has commenced.

Cladding:- Cladding units to both north and south are virtually installed apart from those left out for access.

Glass Atrium Roofs:- The north atrium roof is complete. The south minor atrium has glass substantially installed, while south major atrium has over 85% glazed.

Reconstituted Stone & Brise Soleil:- The Stone contractor Techrete are largely complete on the north and are 80% on the south block with the stone fins that surround the windows, with a priority to those above the Entrance. Brise Soleil is following to both blocks.

Lifts:- The lift contractor Thyssen have completed both car lifts & both passenger lifts, and is currently engaged on the goods lift .

Mechanical & Electrical:- Both the power and water are now connected and the gas supply is expected imminently. Commissioning has commenced and will test and balance each system.

Internal Fitout:- All zones have commenced on the north and south buildings. Decoration is continuing in the north, while floor boxes, door installation continue in the south. The birdcage scaffold is expected to be removed wc 8/4/2013. from the large lecture theatre.

Screed:- The sand and cement subfloor to make the area level flat in readiness for stone paving has been laid in the main entrance area. This was mixed by a machine and pumped to the required area.

Joinery:- Timber balustrade panels have started in the south minor atrium.

Smoke Curtains:- Smoke curtain boxes have been installed in the north. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- The crane base has been broken up and removed. Drainage connections are near to completion around the building. Hard landscaping will now begin progressively to the perimeter of the building, while co-ordinating with cladding finishes.

Recent Site Photos

[bg|new-building/site-visits/20130404|0]
Please contact us with feedback and comments about this page. Created on 05 Apr 2013 - 12:34.

Mathematics Oxford Sculpture Competition

We are inviting artists to propose, and eventually create, a substantial and artistically significant sculpture to be placed in the main Entrance Lobby of the New Mathematical Institute. The New Mathematical Institute building, designed by Rafael Viñoly Architects, is nearing completion in the Radcliffe Observatory Quarter, an area under intensive development by the University of Oxford. It is envisaged that the art work will in its conception be inspired by, or connected to, a mathematical theme, concept or shape.

Full details of the sculpture competition are available

Please contact us with feedback and comments about this page. Created on 24 Mar 2013 - 10:50.

New Building Construction: Progress Update 37

General

Cranes & Fork Lifts:- The loading bay of the south block has been closed off with cladding panels installed. The south block is served with tower crane TC1 and will be supplemented with roof cranes or mobile cranes.

Future works for March

Architectural Metalwork:- Roof terrace balustrade brackets are being installed. Entrance feature stair is installed together with the main elements of the basement staircases. Stair balustrading are largely installed to core areas.

Waterproofing & Flat Roof:- All roofs have been waterproofed and largely paved where required. Sedum (green roof) planting will commence in April.

Entrance:- The gridwork and glass are expected to begin wc 25.03.13. Two side beams also required to be installed.

Cladding:- Cladding units to both north and south are virtually installed apart from those left out for access.

Glass Atrium Roofs:- The north atrium roof is complete. The south minor atrium main has glass substantially installed, while south major atrium has over 70% glazed.

Reconstituted Stone & Brise Soleil:- The Stone contractor Techrete are largely complete on the north and are 70% on the south block with the stone fins that surround the windows, with a priority to those above the Entrance. Brise Soleil is following to both blocks.

Lifts:- The lift contractor Thyssen have completed both car lifts & both passenger lifts, and is currently engaged on the goods lift .

Mechanical & Electrical:- Both the power and water are now connected and the gas supply is expected imminently. Commissioning has commenced and will test and balance each system.

Internal Fitout:- All zones have commenced on the north and south buildings. Decoration has commenced in the north, while floor boxes, door frame & skirting continue in the south.

Screed:- The sand and cement subfloor to make the area level flat in readiness for stone paving has started in the main entrance area. This is mixed by a machine and pumped to the required area.

Joinery:- Carcass works for balustrading within the South Atrium continues while timber balustrade panels with glass top now virtually complete in the north.

Smoke Curtains:- Carcass works for smoke curtains are installed in the north. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Drainage connections are near to completion around the building. Hard landscaping will now begin progressively to the perimeter of the building, while co-ordinating with cladding finishes.

Recent Site Photos

[bg|new-building/site-visits/20130321|0]
Please contact us with feedback and comments about this page. Created on 22 Mar 2013 - 15:22.

New Building Construction: Progress Update 36

General

Cranes & Fork Lifts:- Tower Crane TC2 has been dismantled while the start of breaking up the concrete base adjacent to St Lukes Chapel is expected to start on w.c.18/3/2013. Although this by its very nature will create some noise, it is hoped that it can be carried out in as short a time as possible. The south block is served with tower crane TC1 and will be supplemented with roof cranes or mobile cranes. Internal materials are largely served by a fork lift and with use of the tower crane when required.

Entrance:- The pedestrian entrance has temporarily moved from Gate 1 to Gate 7 while services are being installed adjacent to Sumerville College.

Visits:- On 8/3/2013 a series of 5 furniture review sessions were held in the building for departmental members.

Future works for March

Architectural Metalwork:- Roof terrace balustrade brackets are being installed. Entrance feature stair is installed together with the main elements of the basement staircases. Stair balustrading continue to core areas.

Waterproofing & Flat Roof:- All roofs have been waterproofed and largely paved where required. Sedum (green roof) planting will commence in April.

Entrance:- The longitudinal steel beams (by SUK/CovCon) commenced w.c. 25/2/2013. This will be followed by gridwork and glass.

Cladding:- Cladding units to both north and south are virtually installed apart from those left out for access.

Glass Atrium Roofs:- The north atrium roof is virtually complete. The south minor atrium has glass substantially installed, while south major atrium has over 50% glazed.

Reconstituted Stone & Brise Soleil:- The Stone contractor Techrete are largely complete on the north and are progressing on the south block with the stone fins that surround the windows, with a priority to those above the Entrance. Brise Soleil is following to both blocks.

Lifts:- The lift contractor Thyssen have completed the first car lift & passenger lift in the north. The passenger lift to the south is virtually complete.

Mechanical & Electrical:- The corridor areas in the north are ongoing. Services contractor, Crownhouse, have installed internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. Cabling and wiring are ongoing. Now that power was energised on 27/2/2013 the testing and commissioning can commence in earnest.

Internal Fitout:- All zones have commenced on the north and south buildings. Door installation has commenced in the north, while door frame and skirting continue in the south.

Joinery:- Carcass works for balustrading within the south atrium continues while timber balustrade panels with glass top continue to be installed in the north.

Smoke Curtains:- Carcass works for smoke curtains are installed in the north. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Drainage connections are ongoing around the building.

Recent Site Photos

[bg|new-building/site-visits/20130307|0]
Please contact us with feedback and comments about this page. Created on 09 Mar 2013 - 09:18.

New Building Construction: Progress Update 35

General

Cranes & Fork Lifts:- Tower Crane TC2 is expected to be dismantled 26th February. The south block is served with tower crane TC1 and will be supplemented with roof cranes or mobile cranes. Internal materials are largely served by a fork lift and with use of the tower crane when required. North atrium movable scaffold has now been removed.

Entrance:- The pedestrian entrance has temporarily moved from Gate 1 to Gate 7 while electrical main cables are drawn through ducts to the power room.

Future works for February/March

Architectural Metalwork:- Roof terrace balustrade brackets are being installed. Entrance feature stair is installed together with the main elements of the basement staircases. Stair balustrading continue to core areas.

Waterproofing & Flat Roof:- All roofs have been waterproofed with 5th levels in the process of paving. Sedum (green roof) planting will commence in April.

Entrance:- Cross beams have been connected to the steel columns ready for a start of the entrance roof works (by SUK/CovCon) on week commencing 25/2/2013.

Cladding:- The north block is complete. All elevations to the south block have panels with mainly corner sections to complete.

Glass Atrium Roofs:- The north atrium roof is virtually complete. The south minor atrium main support beams and gridwork are in place with glass substantially installed. South major atrium has main support beams and glass gridwork partly installed, with temporary cover / “tent” over the northerly area.

Reconstituted Stone & Brise Soleil:- The Stone contractor Techrete are largely complete on the north and are progressing on the south block with the stone fins that surround the windows, with a priority to those above the Entrance. Brise Soleil is following to both blocks.

Lifts:- The lift contractor Thyssen have completed the first car lift & passenger lift in the north. The passenger lift to the south is nearing completion with just testing to complete.

Mechanical & Electrical:- The corridor areas in the north are ongoing. Services contractor, Crownhouse, have installed internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. Cabling and wiring are ongoing. When power on date is achieved the testing and commissioning can commence in earnest.

Internal Fitout:- All zones have commenced on the north and south buildings. Door installation has commenced in the north, while door frame and skirting continue in the south.

Joinery:- Carcass works for balustrading within the at South Atrium continues while timber balustrade panels with glass top continue to be installed in the north.

Smoke Curtains:- Carcass works for smoke curtains are installed in the north. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Drainage adjacent to the north access road is ongoing.

Recent Site Photos

[bg|new-building/site-visits/20130221|0]
Please contact us with feedback and comments about this page. Created on 23 Feb 2013 - 15:43.

New Building Construction: Progress Update 34

General

Cranes & Fork Lifts:- Tower Crane TC2 is expected to be dismantled on 20th February. The south block is served with tower crane TC1 and will be supplemented with roof cranes. Internal materials are largely served by a fork lift and with use of the tower crane when required. The access “moling” hole allowing materials to the lower floors has been closed and formed into the permanent vent.

Entrance:- The pedestrian entrance has temporarily moved from Gate 1 to Gate 7 while electrical mains cables are drawn through ducts to the power room.

Visits:- The Mathematics Department tour took place on the 1/2/2013.

Future works for February

Architectural Metalwork:- Entrance feature stair is installed together with the main elements of the basement staircases. Stair balustrading continue to core areas.

Screeding:-Screeding (sand & cement layer to obtain a flat floor) has continued to toilet areas

Waterproofing & Flat Roof:- 3rd, 4th & 5th level main roofs to the north have been waterproofed and the south has also had the 3rd, 4th and 5th levels waterproofed.

Cladding:- The north block is complete. All elevations to the south block have panels with mainly corner sections to complete.

Glass Atrium Roofs:- The north atrium roof is virtually complete. The south minor atrium main support beams and gridwork are in place with glass substantially installed. South major atrium has main support beams installed, with temporary cover / “tent” over the middle area.

Reconstituted Stone:- The Stone contractor Techrete is largely finished on the north and is progressing on the south block with the stone fins that surround the windows, with a priority to those above the entrance.

Lifts:- The lift contractor Thyssen has completed the first car lift in the north. The passenger lift to the south is nearing completion with just testing to complete.

Mechanical & Electrical:- The corridor areas in the north are ongoing. Services contractor, Crownhouse, has installed internal drainage, sprinklers, ductwork, pipework and containment at the basement & mezzanine. Cabling and wiring are ongoing with the power on date wc 18/2/2013 in order that testing and commissioning can commence.

Internal Fitout:- All zones have commenced on the north and south buildings. Door frames continue to be installed in the north & south.

Joinery:- Carcass works for balustrading within the South Atrium continues while timber balustrade panels with glass top continue to be installed in the north.

Smoke Curtains:- Carcass works for smoke curtains started on 21/1/2013. A smoke curtain, when deployed in the event of a fire, will direct smoke away from escape routes.

External Works:- Drainage along the north has commenced.

Recent Site Photos

[bg|new-building/site-visits/20130207|0]
Please contact us with feedback and comments about this page. Created on 09 Feb 2013 - 14:51.

Ben Green to become Waynflete Professor

We are delighted to announce that Professor Ben Green FRS will join us as the new Waynflete Professor of Pure Mathematics. Ben is an outstanding mathematician who is well known for his work in additive combinatorics among other topics. He has held chairs at Bristol and Cambridge.

Please contact us with feedback and comments about this page. Created on 08 Feb 2013 - 20:07.